Map
56 projects, plotted
55 of 56 plotted. Not plotted: Google Virginia expansion — no site, county or city in source.
Hover, tap or focus a state or project point.
Projects by state
| State | Tier | Projects | Disclosed planned GW | Live GW | Latest signal |
|---|---|---|---|---|---|
| Texas (TX) | Filing-stage depth | 9 | 8.000 | 0.80 | 30 Sep 2026 |
| Louisiana (LA) | Filing-stage depth | 4 | 5.545 | 0.00 | 15 Oct 2026 |
| Wisconsin (WI) | Tier A — source-verified | 2 | 3.500 | 0.40 | — |
| Indiana (IN) | Tier A — source-verified | 2 | 3.200 | 1.10 | — |
| New Mexico (NM) | Tier A — source-verified | 1 | 2.400 | 0.00 | — |
| Tennessee (TN) | Tier B — partially verified | 1 | 2.000 | 1.70 | — |
| Mississippi (MS) | Tier C — not yet covered | 1 | 1.800 | 0.60 | — |
| Michigan (MI) | Tier A — source-verified | 1 | 1.400 | 0.00 | — |
| West Virginia (WV) | Tier B — partially verified | 1 | 1.300 | 0.00 | — |
| Ohio (OH) | Tier A — source-verified | 1 | 1.000 | 0.60 | — |
| Georgia (GA) | Filing-stage depth | 22 | 0.900 | 0.90 | 12 Oct 2026 |
| Arizona (AZ) | Filing-stage depth | 6 | 0.225 | 0.00 | — |
| Virginia (VA) | Filing-stage depth | 4 | Not disclosed | 0.00 | — |
| Wyoming (WY) | Tier A — source-verified | 1 | Not disclosed | 0.00 | 5 Nov 2026 |
Virginia planned GW: CleanArc’s “nearly 1 GW critical grid capacity” is not a load figure and is not counted — see ledger. Georgia: 22 projects = Fairwater Atlanta + Southeast Data Center Campus + 20 DRI filings.
Signals
Latest signals — 29 most recent
CyrusOne Thad Hill
Constellation Energy 10-Q confirms CyrusOne at Thad Hill, Bosque County: 400 MW of Calpine power agreements; campus building, first building expected operational Q4 2026.
Google Cheyenne
Google announces its first Wyoming data center, a $17B long-term investment in Laramie County (partners: Tallgrass, Black Hills, AEP, Related Digital)
Delta Forge 1
LPSC Order U-38035 procedural only; consideration by March 2027, NOT an approval
Nixon Technology Center
DRI #4853 Initial Information Form submitted
Hyperion
U-37882 evidentiary hearing Oct 7–9; settlement filed; LPSC decision expected Dec 2026
Medina Project
PUCT Docket 60356 complaint & appeal of ERCOT decisions filed
Social Circle Data Center
DRI #4846 Initial Information Form submitted
Medina Project
ERCOT classifies Medina as studied load (conditional)
Newton County Technology Park
DRI #4843 Initial Information Form submitted
Amazon NW Louisiana
Total planned investment raised to $18B; third campus, Shreveport
Project Granite
DRI #4835 Initial Information Form submitted
River Bend (Hut 8)
Q2 2026 results: under construction; initial hall Q2 2027
Hyperion
Meta + LED: total commitment now more than $50B; 5 GW IT capacity
Delta Forge 1
Cleco files LPSC U-38035 (ESA, interconnection, new generation, waivers)
Delta Forge 1
LED confirms location: Rapides Parish (Boyce), $3.6B, Cleco power
Project Camellia
DRI #4801 Initial Information Form submitted
Hyperion
LDEQ EDMS permit documents, AI 251425
Stillwater Technology Park
DRI #4794 Initial Information Form submitted
Whitetail Crossing
DRI #4797 Initial Information Form submitted
Delta Forge 1
15-yr lease signed: unnamed hyperscaler, 300 MW, ~$7.5B contracted value
Hyperion
LPSC filing U-37882 Phase 2 power package (Evest LLC) — NOT approved
Augusta Corporate Park
DRI #4761 Initial Information Form submitted
Amazon NW Louisiana
$12B campuses announced, Caddo + Bossier (superseded by $18B, Aug 2026)
CyrusOne Freestone
CyrusOne Freestone: Constellation/Calpine announce 380 MW agreement plus exclusive 380 MW Phase 2, Freestone County, TX.
Project Sail
DRI #4736 Initial Information Form submitted
West Midtown Data Center
DRI #4735 Initial Information Form submitted
Kingston Technology Park
DRI #4727 Initial Information Form submitted
Delta Forge 1
Applied Digital breaks ground (430 MW campus; location then undisclosed)
Harbor Park Technology Center
DRI #4689 Initial Information Form submitted
Calendar
Key dates
Cochise County P&Z hearing
Tombstone Resources SU26-22. Watch item — not a tracked project.
LPSC consideration — Hyperion Phase 2
Docket U-37882.
LPSC consideration by B&E Session
Delta Forge 1 / Cleco — Docket U-38035.
River Bend — initial data hall
Company-stated date, Hut 8.
Terafab — construction start (company-stated)
Grimes County, TX · Phase 1 $16.8B · ground broken 6 Oct 2026 · on-site gas + battery; TCEQ air permits on watch.
Live share of disclosed planned capacity
6.1 GW live of 31.3 GW disclosed planned.
Newsletter $49/mo · Pro $199/mo · Team $399/mo · Lead packs $999 each — 56-project registry, updated weekly.
Ledger
All 56 tracked projectsFree
| Project | State | Location | Status | Tenant | Developer | Planned | Live |
|---|---|---|---|---|---|---|---|
| Total — 23 projects with disclosed capacity (table in Data, below) | 31.270 GW | 6.10 GW | |||||
Numbers
The 18 largest campuses
Capacity by status — 18 largest campuses
- 6.1 GW live — 20.3% of the 30.0 GW planned at these 18 campuses
- 7.3 GW — planned, not yet live, at campuses already partly running
- 16.6 GW — planned at campuses with nothing live
10 of 18 campuses have nothing live — 16.6 GW planned.
1 campus fully live: Fairwater Atlanta — 0.9 of 0.9 GW, Microsoft, Georgia.
Highest live shares: Colossus 1+2 85% (1.7 of 2.0 GW) · Prometheus 60% (0.6 of 1.0) · Project Rainier 50% (1.1 of 2.2).
Source: RevenueFlow (Ben Carden), Epoch AI data, 12 Oct 2026. Live figures are Epoch AI estimates.
Planned capacity by tenant — 18 largest campuses
Abilene counted once, under OpenAI. Sums to the 30.0 GW total for these 18 campuses.
Data
The 31.3 GW, project by project
| Project | Planned GW | Live GW |
|---|---|---|
| Hyperion | 5.000 | 0.00 |
| Fairwater | 2.600 | 0.40 |
| Stargate New Mexico | 2.400 | 0.00 |
| Project Rainier | 2.200 | 1.10 |
| Stargate Abilene | 2.100 | 0.60 |
| Colossus 1+2 | 2.000 | 1.70 |
| Ridgeland + Canton | 1.800 | 0.60 |
| Stargate Shackelford | 1.400 | 0.00 |
| Stargate Michigan | 1.400 | 0.00 |
| Monarch | 1.300 | 0.00 |
| Stargate Milam | 1.200 | 0.00 |
| Fort Wayne | 1.000 | 0.00 |
| Goodnight | 1.000 | 0.00 |
| Prometheus | 1.000 | 0.60 |
| El Paso | 1.000 | 0.00 |
| Stargate Wisconsin | 0.900 | 0.00 |
| Fairwater Atlanta | 0.900 | 0.90 |
| Helios | 0.800 | 0.20 |
| Medina Project (Medina Technology Park) | 0.500 | 0.00 |
| Delta Forge 1 | 0.300 | 0.00 |
| River Bend (Hut 8) | 0.245 | 0.00 |
| EdgeCore Mesa campus | 0.225 | 0.00 |
| CleanArc ‘VA1’ campus | As stated: nearly 1 GW critical grid capacity — not a load figure, not in the totals | |
| Total — 23 projects with disclosed capacity | 31.270 | 6.10 |
| 33 of 56 projects: no capacity disclosed — counted as zero, never estimated. | ||
Sources
Reporting & sources
Further reporting on tracked projects. Groundwire’s figures come from the primary documents — press coverage is context, never the source of a figure.
Press coverage
Primary documents
| Publication | Headline | Date | Project |
|---|---|---|---|
| Hut 8 — press release | Hut 8 Signs 15-Year, 245 MW AI Data Center Lease at River Bend Campus… | Dec 17, 2025 | River Bend (Hut 8) |
| Amazon — company news | Amazon to invest $18 billion in Louisiana for new data centers | Updated Aug 18, 2026 | Amazon NW Louisiana |
| Applied Digital — fiscal Q4/FY2026 results | Delta Forge 1 lease: 300 MW, ~$7.5B base-term contracted revenue | Jul 27, 2026 | Delta Forge 1 |
Also on record: PUCT · ERCOT · Georgia DCA DRI portal · Atlanta Regional Commission · Louisiana PSC · Louisiana DEQ EDMS · Virginia Economic Development Partnership.